Atlantis Logo

      Atlantis (OV-104)

      Background

        Atlantis, the fourth orbiter to become operational at Kennedy Space Center, was named after the primary research vessel for the Woods Hole Oceanographic Institute in Massachusetts from 1930 to 1966. The two-masted, 460-ton ketch was the first U.S. vessel to be used for oceanographic research. Such research was considered to be one of the last bastions of the sailing vessel as steam-and-diesel-powered vessels dominated the waterways.

        The steel-hulled ocean research ship was approximately 140 feet long and 29 feet wide to add to her stability. She featured a crew of 17 and room for five scientists. The research personnel worked in two onboard laboratories, examining water samples and marine life brought to the surface by two large winches from thousands of feet below the surface. The water samples taken at different depths varied in temperature, providing clues to the flow of ocean currents. The crew also used the first electronic sounding devices to map the ocean floor.

        The spaceship Atlantis has carried on the spirit of the sailing vessel with several important voyages of its own, including the Galileo planetary explorer mission in 1989 and the deployment of the Arthur Holley Compton Gamma Ray Observatory in 1991.

        In the day-to-day world of Shuttle operations and processing, Space Shuttle orbiters go by a more prosaic designation. Atlantis is commonly refered to as OV-104, for Orbiter Vehicle-104. Empty Weight was 151,315 lbs at rollout and 171,000 lbs with main engines installed.

      Upgrades and Features

        Atlantis benefited from lessons learned in the construction and testing of Enterprise, Columbia and Challenger. At rollout, its weight was some 6,974 pounds less than Columbia. The Experience gained during the Orbiter assembly process also enabled Atlantis to be completed with a 49.5 percent reduction in man hours (compared to Columbia). Much of this decrease can be attributed to the greater use of thermal protection blankets on the upper orbiter body instead of tiles. During the construction of Discovery and Atlantis, NASA opted to have the various contractors manufacture a set of 'structural spares' to facilitate the repair of an Orbiter if one was damaged during an accident. This contract was valued at $389 million and consisted of a spare aft-fuselage, mid-fuselage, forward fuselage halves, vertical tail and rudder, wings, elevons and a body flap. These spares were later assembled into the orbiter Endeavour. Atlantis was shipped to California to undergo upgrades and modifications. These modifications include a drag chute, new plumbing lines that configure the orbiter for extended duration, more than 800 new heat protection tiles and blankets and new insulation for the main landing gear doors, structural mods to the Atlantis airframe. Altogether, 165 modifications were made to Atlantis over the 20 months it spent in Palmdale, California.

      Construction Milestones

      01/29/79 Contract Award
      03/03/80 Start structural assembly of Crew Module
      11/23/81 Start structural assembly of aft-fuselage
      06/13/83 Wings arrive at Palmdale from Grumman
      12/02/83 Start of Final Assembly
      04/10/84 Completed Final Assembly
      03/06/85 Rollout from Palmdale
      04/03/85 Overland transport from Palmdale to Edwards
      04/09/85 Delivery to Kennedy Space Center
      09/05/85 Flight Readiness Firing
      10/03/85 First Flight (51-J)
      5/14/10 Final Scheduled Flight STS-132

      Atlantis's Flights to date:

      01. 51-J (10/3/85)
      02. 61-B (11/26/85)
      03. STS-27 (12/2/88)
      04. STS-30 (05/04/89)
      05. STS-34 (10/18/89)
      06. STS-36 (02/28/90)
      07. STS-38 (11/15/90)
      08. STS-37 (04/05/91)
      09. STS-43 (08/02/91)
      10. STS-44 (11/24/91)
      11. STS-45 (03/24/92)
      12. STS-46 (07/31/92)

      To Palmdale 10/92 for Orbiter Maintenance Down Period (OMDP-1). 165 modifications were made over 20 months including the installation of a drag chute, new plumbing lines to configure the orbiter for extended duration, more than 800 new heat tiles and blankets, new insulation for main landing gear and structural mods to the airframe.

      13. STS-66 (11/03/94)
      14. STS-71 (6/27/95)
      15. STS-74 (11/12/95)
      16. STS-76 (03/22/96)
      17. STS-79 (9/16/96)
      18. STS-81 (1/12/97)
      19. STS-84 (5/15/97)
      20. STS-86 (9/25/97)
      21. STS-101 (5/19/00)


      Left the KSC SLF 11/11/97 for Orbiter Maintenance Down Period (OMDP-2). Arrived in Palmdale 11/14/97 and mods completed 9/24/98. 130 mods included glass cockpit displays, replacement of TACAN navigation with GPS and ISS airlock and docking install. Weight reduction program replaced AFRSI insulation blankets on upper surfaces with FRSI and lightweight crew seats were installed. EDO package installed on OMDP-1 was removed to lighten Atlantis to better serve its prime mission of servicing the ISS.

      22. STS-106 (9/8/00)
      23. STS-98 (2/07/01)
      24. STS-104 (7/12/01)
      25. STS-110 (4/8/02)
      26. STS-112 (10/7/02)
      27. STS-115 (9/9/06)
      28. STS-117 (6/8/07)
      29. STS-122 (2/7/08)
      30. STS-125 (5/11/09)
      31. STS-129 (11/16/09)
      32. STS-132 (5/14/10)
      33. STS-135 (7/8/11)


      On November 2, 2012, Atlantis was driven on a 9.8 mile journey from Kennedy Space Center's Vehicle Assembly Building (VAB) thru the industrial area of Kennedy Space Center and then to its new home at the Kennedy Space Center's Visitor Complex. It will make its museum debut in July, 2013.

      Atlantis Flight Logs (final):

      33 flights
      125,935,769 statute miles
      4848 orbits
      307 days in space

      Science Home Page Return to KSC Science Home Page Other Orbiter Vehicles Other Orbiter Vehicles


      Last Updated Monday, May 17 08:11:52 EDT 2010
      Jim Dumoulin (dumoulin@titan.ksc.nasa.gov)