Return to "SHUTTLE AVIONICS - Design Constraints & Considerations - A Guide Book"


GENERAL 1.

INSTRUMENTATION COEFFICIENTS

Consideration

Due to performance requirements of various systems, sensor unique coefficient information is required

Impact

Design Objectives


GENERAL 2.

TELEMETRY DATA AVAILABILITY

Constraint

Multiple configurations of telemetry data stream constrains testing

Impact

Design Objectives


GENERAL 3.

AVIONICS COOLING

Constraint

Ground support for avionics LRU cooling required to operate avionics. In addition, avionics cooling requirements limit avionics activation and emergency power down responsiveness

Impact

Design Objectives


GENERAL 4.

CONNECTOR RETEST

Constraint

Any connector demate requires continuity verification of every pin on that connector in order to certify functional integrity.

In some cases, the design precludes the use of functional retest to verify connector functions and required level of available redundancy. More exotic means must be used, such as Break-out-Box installation (an example is the Brake/Skid Control Box Fails that are OR’ed together at a Load Control Assembly, thus requiring intrusive means to determine particular Fail functionality or required level of available power redundancy.

Impact

Design Objectives


GENERAL 5.

CONNECTOR MATED INDICATION

Consideration

Presently no way to automatically verify if all connectors are mated prior to testing.

Explanation: It is often required for hazardous or critical operations to know if a system’s electrical configuration is operational. Example: an actuator must have at least one channel of control with hydraulic power applied. If no channels are connected, there is no control of the actuator. The rudder/speedbrake was once powered up hydraulically without knowledge that the command path connections were demated for troubleshooting not associated with actuator control itself. As a result, there was damage to the actuator. This could be economically disastrous if a gimballing engine moved in an uncontrolled manner into another engine (reference GNC 2. Engine Collision), or pose a safety hazard to personnel.

Impact

Design Objectives


GENERAL 6.

PARALLEL SWITCH CONTROL

Consideration

Lack of parallel cockpit switch control from the ground on the Shuttle constrains automation

Impact

Design Objectives


GENERAL 7.

MAN-IN-THE-LOOP

Constraint

Many Shuttle systems require Man-in-the Loop to perform system testing causing serial time impacts and variability of the servicing, maintenance and checkout processes

Impact

Design Objectives


GENERAL 8.

AVIONICS LRU ACCESS / MOUNTING

Constraint

Improve avionics line replaceable unit (LRU) access.

Impact

Design Objectives


GENERAL 9.

AVIONICS LRU FASTENING DEVICES

Consideration

Fastening devices for installing avionics components should provide for trouble-free removal and installation and guaranteed for the lifetime of the vehicle (i.e., repetitive use).

Explanation: Many of the fasteners used for Shuttle avionics components have been unreliable and costly to replace. The use of stainless steel inserts and stainless steel bolt and captive fasteners have led to galled threads, inability to install or remove, and uncertainty of flight certification torque values at the time of installation. Many fasteners require the measurement of running torque and final torque. In addition, the self-locking features of many of these fasteners are not satisfactory for repetitive installations. Costly component damage has resulted from these design deficiencies.

Impact

Design Objectives


GENERAL 10.

AVIONICS LRU GROUND HANDLING EQUIPMENT

Constraint

The removal/reinstallation of many avionics components requires special ground support equipment (GSE).

Impact

Design Objectives


GENERAL 11.

AVIONICS BITE / TEST POINTS

Consideration

Lack of Built-In-Test-Equipment (BITE) and test monitoring points (available in the telemetry data stream) constrains the ability to know whether the required level of redundancy is available for commitment to flight (and retention of system certification from launch to launch). Also delays problem isolation.

Impact

Design Objectives


GENERAL 12.

CRITICAL REDUNDANT POWER VERIFICATION

Consideration

Equipment's redundant power should be verified automatically upon power on.

Impact

Design Objectives


GENERAL 13.

SOFTWARE IN END-ITEM

Consideration

Software functions which are not embedded in the end item may result in added ground support personnel due to tendency to over-mange centralized software.

Impact

Design Objectives


GENERAL 14.

LOCAL OPF OPERATION

Consideration

Remote firing room control constrains OPF operations

Impact

Design Objectives


GENERAL 15.

UNPLANNED WORK

Constraint

Unplanned troubleshooting, repair and retest are way too high : approx. 50 %

Impact

Design Objectives


GENERAL 16.

VENDOR DRAWINGS

Constraint

Lack of Vendor drawings, specifications constrains testing and troubleshooting

Impact

Design Objectives


GENERAL 17.

HYDRAULICS

Constraint

Hydraulic systems cost enormous processing resources

Impact

Design Objectives


Return to KSC Next Gen Site

Edgar Zapata, NASA Kennedy Space Center

Shuttle Process Engineering Directorate, Fluid Systems Division