On Friday, February 22, 2002, final pre-launch processing for Shuttle
Columbia continues on schedule at Complex 39 Pad A . The Hubble
payload Interface Verification Test is complete and the End-To-End
Test is in progress. Work over the weekend includes completing aft
closeouts prior to picking up the final countdown at the T-43 hour
mark at 10 a.m. Monday, Feb. 25. The seven STS-109 crewmembers are
scheduled to land at KSC at 1 a.m. Monday, and shortly after their
arrival they will spend about two hours at the launch pad
participating in final Hubble payload configuration familiarization
operations in preparation for the five spacewalks that will be
conducted during the STS-109 servicing mission. The payload doors will
be closed later in the day. The status of the Auxiliary Power Unit
hydraulic pump bolts is still under evaluation. (Reference KSC Shuttle
Status 2/22/2002)
On 1/28/02, Shuttle Columbia rolled out to Launch Complex 39A and is
undergoing final preparations. The main engine Flight Readiness Test
is complete and the two-day Countdown Demonstration Test (CDT) is
underway, with a T-0 at 11 a.m. on Friday. The seven STS-109
crewmembers will be at the launch pad for familiarization and
emergency egress operations today and will be onboard Columbia
tomorrow to participate in the final hours of the simulated countdown.
(Reference KSC Shuttle Status 1/31/2002)
The rollout of Shuttle Columbia from the Vehicle Assembly Building
(VAB) to Pad 39A was rescheduled for no earlier than Saturday morning
due to requirements to continue trouble-shooting and verifying a
faulty bearing in the steering linkage on one of the
crawler-transporter's (CT) four "trucks." In addition, NASA management
mandated that all of the trucks on the CT be inspected and verified
prior to commencing rollout activities. The rollout had been scheduled
for Wednesday, Jan. 23, but was delayed due to th crawler problem. No
impact to the prelaunch milestones or launch date is expected.
(Reference KSC Shuttle Status 1/24/2002)
On January 17, 2002, Columbia rolled over from the OPF into the
Vehicle Assembly Building (VAB). (Reference KSC Shuttle Status 1/17/2002)
The launch date for STS-109 was earlier pushed back to give
engineers time to evaluate a reaction wheel problem on the Hubble
Space Telescope. Previous launch dates were February 14, 2002,
January 17, 2002, January 11, 2001 and before that November 19, 2001.
STS-109 Movies and Images
Note:
The image on this page is from an NTSC video capture that is updated every minute from the T-5 hour mark on the countdown until launch. At all other times, the view is either connected to the NASA TV (NTV) feed (Click here for Video Advisories) or it is a static video capture of an Orbiter Television (OTV) camera that is updated a few times a day. If you have a WWW browser that caches images, you may need to select "Reload" periodically to see these images change. You may also want to look into getting your own live NASA Television Feed by loading CU-SeeMe on your system.
STS-109 Countdown
Last Mission STS-108
Next Mission STS-110
Developed under the direction of the NASA KSC Public Affairs Office
Author: Jim Dumoulin (dumoulin@titan.ksc.nasa.gov) / NASA - Payload Operations
Last Updated: Monday April 1 17:51:34 EDT 2002(J.Dumoulin)
A service of NASA/Kennedy Space Center Public Affairs Office, Joe Gordon Jr.,Director (Joseph.Gordon-1@ksc.nasa.gov)